Neuville, QC

Treating water at an environmental complex, without discharge

Neuville Environmental Complex

Back to Evaplant®
Planting 2023 · In operation since 2024
96,000
Willows planted
~20,000 m³/year
Treatment capacity
6 ha
Planting area
Former LET
Valorized by the project

Context

The Neuville Environmental Complex, managed and operated by Récolo, processes several streams of residual materials, including septic sludge and the water generated by its environmental facilities.

Récolo chose to act proactively on an issue facing many landfills: reducing the volume of leachate to be treated and discharged into the Jacques-Cartier River, relieving its water treatment plant, already close to capacity, and equipping itself with a tool for managing emerging contaminants such as PFAS.

The project also aimed to valorize a closed former landfill cell by establishing a productive environmental infrastructure on it.

Aerial view of the Neuville Environmental Complex along the river, Quebec
The Neuville Environmental Complex, along the Jacques-Cartier River.

The solution implemented

Ramo installed an Evaplant® system on the final cover of a former landfill at the Neuville Environmental Complex.

The system is based on:

  • controlled irrigation of effluents
  • distribution to the root zone of the willows
  • automated management of water inputs
  • high-density planting of fast-growing willows

The planting acts as a no-discharge treatment infrastructure integrated into the site's operations, which reduces the volumes of water directed toward conventional treatment facilities accordingly.

Evaplant® control centre and willow planting at the Neuville Environmental Complex, Quebec
Evaplant® control centre and planting, integrated into the complex's operations.

Results and performance

Treatment without discharge

Treatment capacity without discharge of up to roughly 20,000 m³ per year.

Site valorization

Transformation of a former landfill cell into an active environmental infrastructure.

Agronomic performance

Planting of roughly 96,000 willows over an area of 6 hectares.

Preserved infrastructure

Reduced pressure on the complex's water treatment plant, already close to capacity, which helps defer investments.

Evaplant® willows backlit in full growth at the Neuville Environmental Complex, Quebec
Fast-growing willows at peak season (the biomass that evapotranspires the effluents).

Client testimonial

“This project allows us to manage our resources and facilities intelligently while improving our environmental performance.”

Bernard Gaudreau (Chair of Récolo, Mayor of Neuville and Warden of the Portneuf RCM at the time of the project announcement, September 2025)

The project received financial support from Tree Canada.

Co-benefits

Preserved infrastructure

Less water to treat: the plantation relieves the complex's treatment plant, already close to capacity, and helps defer investments.

A healthier Jacques-Cartier River

Every litre evaporated by the willows is one litre less in the river: a direct gain for ecosystems and for sensitive species such as salmon.

Better management of emerging pollutants

A team from the Institut de recherche en biologie végétale (IRBV) is monitoring the willows' ability to retain persistent contaminants such as PFAS.

Carbon captured and organic matter produced

The willows capture carbon and produce biomass that is turned into organic matter used in the complex's operations.

Evaplant® project announcement in the field at the Neuville Environmental Complex, Quebec
Project announcement on site (a demonstration of phytotechnologies in residual materials management).
Back to the Evaplant® solution

A similar challenge?
Contact us.

Our team is available to discuss your needs and recommend the right solution.